| Further progress news has come from Geodynamics Ltd. Savina 1 was drilling the Patchawarra Formation at 3244 m. Under-balanced drilling had increased the rate of penetration. At Habanero, the Turbine Hall and Visitor Centre have been completed, while work continues on the power plant. The closed-loop flow testing officially commenced, so the six-week flow-test should be completed late January. |