Previous Week | Week 29 | Next Week![]() | ||||||||
|
There are no events on this week |
||||||||||
|
||||||||||
|
||
| Geodynamics Ltd has announced the commencement of its fifth hole in the Cooper Basin. Savina-1 began on Saturday 18th and has grown to a 564 m depth and 24” diameter. Target depth is 4300 m. Meanwhile, construction work is progressing on the turbine hall for the 1 MW demonstration power plant that will provide Innaminka with free electricity. At Habanero GDY is continuing to work with Schlumberger to get the circulation pump back on site and operating. |