| Green Rock Energy stress test results |
|
|
|
| Sunday, 01 July 2007 | |
| Green Rock Energy also had some interesting news to tell on Monday 2. CSIRO has completed a stress field analysis of GRK’s Blanch project near Olympic Dam. The results confirm that the stress field is ideal for the hydraulic enhancement of sub- horizontal fracture systems in the granite underlying the project, the optimal conditions for developing an underground heat exchanger. |
| < Prev | Next > |
|---|
| Geodynamics announced drilling of Savina 1 has reached 2300 meters. Making further progress, the construction of the Turbine Hall and Visitor Centre at Innaminka 1MW power plant are going well, with commission of the plant proposed for early 2009. |