Flow From Habanero 3
On the 26th of February, Geodynamics announced that Habanero 3 has flowed steam as part of the well clean up program prior to flow testing.
The well flowed at approximately 23kg/sec and the hydraulic connection with Habanero 1 was reconfirmed, with good indication of well productivity.
|
| < Prev | Next > |
|---|
|
Flow test commenced 14th March 2008
On the 17th of March 2008, Geodynamics announced that Habanero 3 well was first opened under controlled flowing conditions on Friday 14 March 2008. The well is sustaining production of 18 kg/second at a flowing pressure of 27.5 MPa (3,990 psi) through a 12.5mm fixed choke. Current flowing temperature is 208 °C. The flow is directed to a steam separator designed for up to 25 kg/second input. In one short experiment lasting 3 minutes the variable choke was opened to 100% and production of 40 kg/second was sustained over that period. |