Circulation Test 75% Complete PDF Print E-mail
Thursday, 05 February 2009
Geodynamics Ltd has declared that its Habanero circulation test was 75% complete. The test had circulated brine for 31 of the required 42 days. Completion was expected in late February. Meanwhile, operations at Savina 1 had successfully recovered 400 m of the stuck drill pipe.
 