Green Rock Energy released more information about their Hungary project PDF Print E-mail
Monday, 26 March 2007
Green Rock Energy released more information about their Hungary project in an open briefing on Monday 26th March. Sustained flow rates at Ortaháza 5 were approximately 1,100– 1,200 cubic metres per day. A flow rate of 2,200 cubic metres per day was required to support a geothermal power plant. 

Flow rates in excess of the required levels have been achieved in the Pannonian Basin before, and GRK remains confident about the overall project. The next test location will be selected from the zone in the Pannonian Basin where the best water flow rates can be expected.
 